|
FUNCTIONALITY HIGHLIGHTS
- dynamic announcements
- dynamic file sharing
- dynamic message board
- file uploading
- error checking
TIMELINE
9 weeks total from design to deployment
(including content management system)
- design requirements: 1 week
- database design: 0.5 weeks
- logic programming: 6 weeks
- graphic design: 1 week
- content preparation: 0.5 weeks
WEB APPLICATION TECHNOLOGY
Active Server Pages
WEB SERVER & TOOLS
IIS, FrontPage
DATABASE
Microsoft Access
DESIGN TOOLS
Fireworks, Photoshop, FrontPage
|